LANGUAGE:
EN CN
RU
500kV DC de-icer was successfully put into operation

On October 29, 2021, after more than 50 hours of continuous test, the DC de-icing equipment of 500kV Tianxing intelligent substation  successfully completed the current raising operation with the line. NR has added another high-capacity DC de-icier in China Southern Power Grid.

Tianxing substation is the second 500kV smart station of Yunnan power grid. It was put into operation in July 2021. The rated capacity of the de-icing equipment is 103MW and the rated output DC current is 5000A, which can meet the DC de-icing requirements of 500kV Tianxi line A and B.

After on-site installation and commissioning, NR service team has completed various acceptance works. On October 27, it was officially started and put into operation. After two days and two nights of live test, the 5000A short-circuit current rise of the de-icing system was realized without abnormality, and the current rise of the de-icing system with 500kV line conductor and ground wire was realized. The smooth operation indicates that the DC de-icing of Tianxing substation has the ability of emergency de-icing to protectpower supply in winter.

image.png

Field test of DC de-icing of Tianxing substation


image.png

DC de-icing converter valve of Tianxing substation


At present, NR has successively put into operation more than 80 sets of DC de-icing equipment in various regions of the country to escort the stable and reliable operation of the power grid.

NR will always create value and serve the society with professional skills and high-quality and reliable services to ensure the normal operation of power grid in snow season.


Back to list

© Copyright NR Electric Co., Ltd.
All Rights Reserved.

About us Service & Support Company Training Contact Us

Solutions Power Generation Transmission System Distribution Network Industrial Consumer

Products Protection,Automation&Control FACTS HVDC Renewable & Microgrid